Electricity staff clean solar panels at An Hoi - Con Dao Power Plant (photo: baobariavungtau.com.vn) |
Investment in national grid power is seen as the most feasible plan. Deputy Prime Minister Le Van Thanh has assigned the Ministry of Industry and Trade to assess the investment project of a power grid for Con Dao.
It will include more than a 23 km electric line, 73 km of submarine cable, and 6.1 km of underground cable. Truong Van Thoi, Deputy Director of the provincial Department of Industry and Trade said Con Dao islanders are scheduled to have access to the national electric grid by 2026.